2022 Resurfacing Project

The 2022 resurfacing project is underway in the City of Perrysburg. This year’s project is focusing on resurfacing and curb repairs on five streets. Those streets include Rivercrest Drive, Eckel Junction Road, Fawn Circle, Laurel Lane and Five Point Road. The following work will be done: 

  • Rivercrest Dr. - Full curb replacement, curb ramp replacements, drive apron replacements and resurfacing of the road. 
  • Eckel Junction Road, Fawn Circle and Laurel Lane – Spot curb repairs, curb ramp replacements and resurfacing of the road. 
  • Five Point Road – Pavement repairs and resurfacing of the road. 

The sequence of construction will be as follows: 

  • Concrete removals on half of Rivercrest 
  • Concrete removals on Eckel Junction, Fawn Circle, and Laurel Lane 
  • Pour concrete on Rivercrest, Eckel Junction, Fawn Circle, and Laurel Lane 
  • Concrete removals on the other half of Rivercrest 
  • Pour concrete on Rivercrest
  • Mill and resurface the roads 

All roads will remain open during construction but motorists may see flaggers directing traffic. There will also temporarily be no parking on the affected streets and some sidewalks will be closed. Work is expected to be completed by the end of October.